Aitik and Kevitsa Electrified Mine Transport Expansion
This project is operational in Finland and Sweden. The source does not give a quantified reduction for this project.
- Status
- Operational
- Estimated reduction
- Not quantified in the source
- Countries
- Finland and Sweden
- Sector
- Transport and logistics
- Announced
- Not stated
- Expected start
- 2020
About this project
The description is as the source gives it.
Boliden invested SEK 300 million to expand electrified transport systems at the Aitik (Sweden) and Kevitsa (Finland) open-pit mines, including additional electric trolley lines and conversion of mine trucks to electric operation. The project reduces diesel consumption and greenhouse gas emissions from transportation. Evidence: "Boliden is investing SEK 300 million in the expansion of electrified transport at the two open-pit mines of Aitik and Kevitsa, mainly during 2020-2021." — https://www.boliden.com/sustainability/case-studies/climate-smart/
Statuses, countries and reductions are as the public source states them, and may be out of date.
Project developers can list this project on Carbon3
Project developers can list a project on Carbon3, so that buyers and co-funders can see it. Listing a project costs nothing.